Incorporation of Terms and Conditions: Battle of the Forms – Useful guidance form the High Court (TCC)

Charles Edwards, Barrister and TECBAR Adjudicator reviews a case in the Technology and Construction Court which provides useful guidance on the incorporation of Terms and Conditions and the importance of giving reasonable notice of such Terms and Conditions: Transformers & Rectifiers Ltd v Needs Ltd [2015] EWHC 269 (TCC). The Claimant and the Defendant entered […]
BEWARE: PAYMENT AND CONSTRUCTION CONTRACTS: GUIDANCE FROM THE HIGH COURT (TCC)

The Technology and Construction Court in Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC) provided much needed and useful guidance in relation to payments arising payments arising from construction contracts, in particular, Payment Notices and Pay Less Notices. By way of background, on 26 March 2015, the parties entered into a contract incorporating the […]